Prepare & ramp down:

  • Prepare racks (cabling, power, network)
  • buildup new “bridgehead” at target & test

Cutover

  • Reduce the workload to 0
  • Shutdown
  • Logical cutover (Transfer active configuration)
  • Startup “bridgehead”
  • Validation
  • Ramp-up
  • Disconnect unused nodes at source
  • De-install servers,
  • Prepare & move the servers
  • Install the servers at target
  • Re-connect & bring into production

Production

  • Ramp-up
  • Aftercare